AI Data Center Stocks

17 GW

mapped gross capacity

Delivery schedule

GW delivery timeline

Each filled bar uses the selected gross capacity basis when available, with legacy capacity called out separately.

Live nowContracted phasesAvailable to contractNot quantified
Contracted ITStatusSource-backedSourceTeraWulf July 2026 8-K / Q1 2026 10-Q / Muskie Data Campus SEC exhibitLast verifiedJul 6, 2026NotesCritical IT-load total includes 438 MW at Lake Mariner, 168 MW at Abernathy, and 401 MW at Hawesville. Abernathy is subject to a definitive sale agreement to a Fluidstack-led investor group, so ownership status needs follow-up. Gross basis remains 2.38 GW and keeps Hawesville's 480 MW gross power availability separate from the Anthropic critical IT-load lease. Cayuga potential critical IT load is displayed as a caveated development fact, not contracted IT load.
5 gross capacity phases + 3 contracted IT phases
AvailableLake Mariner near-term gross capacity · 0.5 GW · near-term capacity · Gross capacityAvailableMuskie initial gross capacity · 0.5 GW · H2 2028 target · Gross capacityAvailableMuskie second gross capacity · 0.5 GW · H2 2030 target · Gross capacityAvailableCayuga potential gross capacity · 0.4 GW · permitting / forward development · Gross capacityAvailableHawesville gross power availability · 0.48 GW · gross site power · Gross capacityContractedLake Mariner contracted IT load · 0.44 GW · 2025-2026 deliveries · Critical IT loadContractedAbernathy contracted IT load · 0.17 GW · development / pre-leased / pending sale · Critical IT loadContractedHawesville Anthropic contracted IT load · 0.4 GW · 2H 2027 initial; full ramp early 2028 · Critical IT load

Gross capacity shown here is available or development capacity; contracted critical IT load is tracked separately.

Key risk: Hawesville starts in 2H 2027 and ramps by early 2028; Abernathy is subject to a pending Fluidstack-led sale; Cayuga and Muskie remain development gross-capacity signals.TeraWulf July 2026 8-K / Q1 2026 10-Q / Muskie Data Campus SEC exhibit
ContractedStatusSource-backedSourceNebius Q1 2026 shareholder letterLast verifiedMay 13, 2026NotesGross-capacity view now uses Nebius current >3.5 GW contracted-power floor. Mapped North American site rows remain 2.7 GW because Alabama and other capacity buckets do not disclose site-specific MW or critical IT load.
4 gross capacity phases breakdown
ContractedVineland AI factory · 0.3 GW · 2025-2026 · Gross capacityAvailableIndependence AI factory · 1.2 GW · 2027+ · Gross capacityAvailablePennsylvania AI factory region · 1.2 GW · 2027+ · Gross capacityContractedOther contracted power floor · 0.8 GW · 2026+ undisclosed allocation · Gross capacity

Track connected power delivery as the swing factor for 2026 revenue scale.

Key risk: Contracted power and connected power are not active revenue-generating IT load; undisclosed site allocation remains below company-level contracted power.Nebius Q1 2026 shareholder letter
Contracted ITStatusSource-backedSourceCore Scientific Q1 2026 SEC earnings deckLast verifiedMay 6, 2026NotesCritical IT-load total remains the 590 MW CoreWeave-contracted leased customer power capacity. Gross-capacity view includes company-deck Pecos and Muskogee total gross power capacity potential; those figures are not treated as contracted critical IT load.
2 gross capacity phases + 2 contracted IT phases
AvailablePecos gross-power roadmap · 1.5 GW · longer-dated development · Gross capacityAvailableMuskogee gross-power roadmap · 1.5 GW · longer-dated development · Gross capacityContractedCoreWeave ramp · 0.45 GW · summer 2026 · Critical IT loadContractedFull contracted load · 0.14 GW · early 2027 · Critical IT load

Gross capacity shown here is available or development capacity; contracted critical IT load is tracked separately.

Key risk: CoreWeave concentration and conversion timing dominate the contracted setup; Pecos/Muskogee are roadmap capacity, not current contracted IT load.Core Scientific Q1 2026 SEC earnings deck
ContractedStatusSource-backedSourceGalaxy Q2 2025 updateLast verifiedAug 5, 2025NotesGross basis uses Galaxy's company-disclosed 3.5 GW total potential power capacity at Helios. Phase I-III gross equivalents total 800 MW and remain separate from 526 MW committed critical IT load.
4 gross capacity phases + 3 contracted IT phases
ContractedPhase I gross power · 0.2 GW · 1H26 expected · Gross capacityContractedPhase II gross power · 0.4 GW · 2027 · Gross capacityContractedPhase III gross power · 0.2 GW · 2028 · Gross capacityAvailableRemaining Helios potential power · 2.7 GW · post adjacent acquisition / development · Gross capacityContractedPhase I · 0.13 GW · 1H26 expected · Critical IT loadContractedPhase II · 0.26 GW · 2027 · Critical IT loadContractedPhase III · 0.13 GW · 2028 · Critical IT load

Delivery cadence is the cleanest public-market check on Helios monetization.

Key risk: Only 526 MW is committed critical IT load; 3.5 GW is total potential power capacity and depends on adjacent acquisition/interconnection development.Galaxy Q2 2025 update
Contracted ITStatusSource-backedSourceGalaxy / Applied Digital / Core Scientific / CoreWeave source reviewLast verifiedJun 8, 2026NotesCritical IT-load total includes Helios 526 MW, Polaris Forge 1 Buildings 1-3 at 400 MW, and Core Scientific 590 MW. Gross-capacity view uses Lancaster's 300 MW company-source potential. Excludes Delta Forge 2 because the customer is not named in the SEC exhibit, and excludes Lancaster from critical IT load because only gross capacity was reviewed.
1 gross capacity phase + 4 contracted IT phases
AvailableLancaster gross capacity · 0.3 GW · future expansion · Gross capacityContractedHelios committed IT load · 0.53 GW · 1H26-2028 · Critical IT loadContractedPolaris Forge 1 Buildings 1-2 · 0.25 GW · 175 MW live as of Jul 2026; remaining Building 2 capacity in buildout · Critical IT loadContractedPolaris Forge 1 Building 3 · 0.15 GW · 2026 lease-assignment MOU · Critical IT loadContractedCore Scientific contracted IT load · 0.59 GW · >450 MW summer 2026; full 590 MW early 2027 · Critical IT load

Gross capacity shown here is available or development capacity; contracted critical IT load is tracked separately.

Key risk: Partner buildout timing and high customer/counterparty concentration can move the trade.Galaxy / Applied Digital / Core Scientific / CoreWeave source review
Contracted ITStatusSource-backedSourceHut 8 Beacon Point releaseLast verifiedMay 6, 2026
1 gross capacity phase + 2 contracted IT phases
AvailableBeacon Point gross electrical campus · 1 GW · future phases · Gross capacityContractedBeacon Point phase 1 IT lease · 0.35 GW · Q1 2027 target · Critical IT loadContractedOther contracted AI capacity · 0.25 GW · 2027+ · Critical IT load

Gross capacity shown here is available or development capacity; contracted critical IT load is tracked separately.

Key risk: More 2027-weighted than the 2026 delivery names.Hut 8 Beacon Point release
ContractedStatusSource-backedSourceApplied Digital June 2026 SEC exhibitsLast verifiedJun 8, 2026NotesCompany-level portfolio total from Delta Forge 2 8-K; mapped site totals are lower because several campuses/customers remain undisclosed. Polaris Forge 1 has 175 MW live as of July 1, 2026. ELN-04 150 MW is tracked as funded development, not promoted to contracted customer capacity.
1 gross capacity phase + 4 contracted IT phases
ContractedContracted gross utility portfolio · 2.2 GW · portfolio · Gross capacityContractedPolaris Forge 1 Buildings 1-2 · 0.25 GW · 175 MW live as of Jul 2026; remaining Building 2 capacity in buildout · Critical IT loadContractedPolaris Forge 1 Building 3 · 0.15 GW · 2026 lease-assignment MOU · Critical IT loadContractedDelta Forge 2 lease · 0.21 GW · Q1 2028 initial operations · Critical IT loadContractedRemaining contracted AI Factory portfolio · 0.79 GW · phased / undisclosed · Critical IT load

APLD shifted from a single-site CoreWeave catalyst to a multi-campus AI Factory portfolio with filed critical IT-load and utility-power totals.

Key risk: Portfolio total includes undisclosed campuses; site-level dashboard should not geocode or allocate undisclosed MW without source detail.Applied Digital June 2026 SEC exhibits
ContractedStatusSource-backedSourceCipher / Fluidstack Barber Lake SEC exhibitsLast verifiedNov 20, 2025NotesBarber Lake critical IT load is 168 MW plus 39 MW expansion. Gross-capacity view now includes Cipher's company-disclosed ~3.2 GW HPC-prioritized pipeline; only 600 MW is mapped to Barber Lake and Black Pearl site rows.
3 gross capacity phases + 2 contracted IT phases
ContractedBarber Lake full gross site capacity · 0.3 GW · full-site lease · Gross capacityAvailableBlack Pearl gross power · 0.3 GW · separate site · Gross capacityAvailableRemaining HPC-prioritized pipeline · 2.6 GW · pipeline / undisclosed sites · Gross capacityContractedBarber Lake initial critical IT · 0.17 GW · Sep 2026 · Critical IT loadContractedBarber Lake expansion critical IT · 39 MW · Jan 2027 · Critical IT load

Barber Lake is contracted proof; the larger signal is Cipher's now-disclosed 3.2 GW HPC-prioritized pipeline.

Key risk: Only 207 MW is sourced as contracted critical IT load; the 3.2 GW pipeline is gross development capacity and not site-level IT load.Cipher / Fluidstack Barber Lake SEC exhibits
Contracted ITStatusSource-backedSourceRiot Q1 2026 results / 2026 business updateLast verifiedApr 30, 2026NotesUpdated for AMD exercise of the additional 25 MW option disclosed with Q1 2026 results. Gross-capacity view now uses the Rockdale 700 MW approved/interconnected site-power figure. The prior 1.7 GW company timeline figure was removed after source audit; Riot's January 2026 business update supports a 1 GW+ critical IT leasing opportunity, not a 1.7 GW gross-capacity total.
1 gross capacity phase + 2 contracted IT phases
AvailableRockdale approved gross power · 0.7 GW · Rockdale site · Gross capacityContractedAMD initial lease · 25 MW · Jan-May 2026 · Critical IT loadContractedAMD option exercise · 25 MW · Q1 2026 · Critical IT load

Gross capacity shown here is available or development capacity; contracted critical IT load is tracked separately.

Key risk: Only 50 MW is contracted critical IT capacity; Rockdale site power is gross-power context, and Riot's 1 GW+ leasing opportunity is not a source-backed gross-capacity total.Riot Q1 2026 results / 2026 business update
ContractedStatusSource-backedSourceDigi Power X 8-KLast verifiedMay 8, 2026
2 reported capacity phases breakdown
ContractedPhase 1 · 15 MW · Delivery Date 1 · Critical IT loadContractedPhase 2 · 25 MW · Delivery Date 2 / conditional · Critical IT load

Small-cap, high-beta catalyst with explicit ready-for-service targets.

Key risk: Phase 2 depends on financing and accelerated construction execution.Digi Power X 8-K
LiveStatusSource-backedSourceIREN location pages and June/July 2026 releasesLast verifiedJul 2, 2026NotesCompany-source North America location pages list Sweetwater 2,000 MW, Oklahoma 1,600 MW, Childress 750 MW, Mackenzie 80 MW, Prince George 50 MW, and Canal Flats 30 MW. IREN's June 15, 2026 Nostrum release adds approximately 490 MW of secured, grid-connected power in Spain, bringing secured portfolio power to about 5.0 GW. IREN's June 3, 2026 Bundey release supports a planned 800 MW South Australia campus, tracked as expansion capacity and kept outside the secured gross total. No reviewed source gives critical IT-load conversion.
8 gross capacity phases breakdown
AvailableSweetwater 1 gross power · 1.4 GW · 2026 substation energization · Gross capacityAvailableSweetwater 2 gross power · 0.6 GW · 2027 substation energization · Gross capacityAvailableChildress gross power · 0.75 GW · existing site · Gross capacityAvailableOklahoma gross power · 1.6 GW · 2028 substation energization · Gross capacityLiveMackenzie gross power · 80 MW · existing site · Gross capacityLiveCanal Flats gross power · 30 MW · existing site · Gross capacityLivePrince George gross power · 50 MW · existing site · Gross capacityAvailableNostrum Spain secured power · 0.49 GW · secured grid-connected power · Gross capacity

IREN's power-bank footprint now spans North America, Europe, and APAC; the conversion question remains signed AI/HPC tenants and disclosed critical IT load.

Key risk: Secured grid-connected power and planned transmission capacity are not contracted AI IT load.IREN location pages and June/July 2026 releases
AvailableStatusSource-backedSourceCleanSpark Q2 2026 releaseLast verifiedMay 6, 2026NotesCompany release cites 585 MW of ERCOT-approved capacity. Keep out of contracted IT-load totals until a site-level AI/HPC lease and critical IT-load basis are sourced.
1 gross capacity phase breakdown
AvailableERCOT-approved gross capacity · 0.59 GW · tenant TBD · Gross capacity

Watch for the first signed AI/HPC lease before treating capacity as delivery.

Key risk: ERCOT-approved gross capacity is source-backed, but no AI/HPC tenant, delivery date, or critical IT-load conversion is disclosed.CleanSpark Q2 2026 release
AvailableStatusSource-backedSourceBitdeer April 2026 updateLast verifiedMay 12, 2026NotesGross-capacity view includes source-tagged AI Cloud / colocation conversion and pipeline sites: Rockdale online 563 MW plus Rockdale pipeline 179 MW, Knoxville 86 MW, Wenatchee 13 MW, Tydal 225 MW, Clarington 570 MW, Niles 300 MW, and Cyberjaya 11.5 MW. Excludes crypto-only capacity and Molde/Fox Creek early-assessment buckets from the promoted subtotal.
8 gross capacity phases breakdown
AvailableRockdale online AI/colo evaluation · 0.56 GW · online / active evaluation · Gross capacityAvailableKnoxville AI Cloud conversions · 86 MW · Q4 2026-Q1 2027 · Gross capacityAvailableWenatchee AI Cloud conversion · 13 MW · Q4 2026 · Gross capacityAvailableTydal colocation conversion · 0.23 GW · Q4 2026 target · Gross capacityAvailableClarington colocation pipeline · 0.57 GW · timing to be updated · Gross capacityAvailableNiles colocation / AI Cloud pipeline · 0.3 GW · Q4 2028 target · Gross capacityAvailableRockdale pipeline colocation / AI Cloud · 0.18 GW · 2026 planning · Gross capacityAvailableCyberjaya AI Cloud capacity · 12 MW · online plus Q4 2026 pipeline · Gross capacity

The dashboard was undercounting the AI/colocation-tagged Bitdeer footprint; tenant conversion remains the gating proof point.

Key risk: The full 3.0035 GW global portfolio includes crypto-only sites; only AI Cloud / colocation-tagged capacity is promoted to this gross-capacity readout.Bitdeer April 2026 update
PlatformStatusNeeds verificationSourceDigitalOcean Q1 2026 slide coverageLast verifiedMay 7, 2026NotesRetains gross and critical IT load as null. Platform capacity phases show the committed capacity signal separately from site-control metrics.
3 reported capacity phases breakdown
AvailableExisting committed platform capacity · 75 MW · committed base · Active capacityAvailableExpected 2026 platform capacity · 31 MW · 2026 · Active capacityAvailableIncremental plan · 29 MW · 2027 · Active capacity

AI platform expansion signal, not a North American site-control thesis.

Key risk: DigitalOcean capacity is platform/cloud capacity, not North American site-control gross power or contracted critical IT load.DigitalOcean Q1 2026 slide coverage
LiveStatusSource-backedSourceHIVE BUZZ HPC / GTA / Yguazu / Boden SEC exhibitsLast verifiedJun 25, 2026NotesCritical IT-load total includes 16.6 MW of Canadian critical IT capacity plus HIVE's June 2026 non-binding Boden LOI for approximately 25 MW usable critical IT load. Gross-capacity view remains 950 MW because Boden's 32 MW gross utility load may already be included in the disclosed operating global data-center power footprint.
4 gross capacity phases + 2 contracted IT phases
AvailableGTA utility capacity · 0.32 GW · H2 2027 target · Gross capacityLiveOperating global data-center power · 0.45 GW · operating footprint · Gross capacityAvailableOther 2027 pipeline capacity · 80 MW · 2027 pipeline · Gross capacityAvailableYguazu Paraguay substation · 0.1 GW · Sep 2026 energization; H2 2027 ready-for-service · Gross capacityLiveManitoba critical IT load · 4 MW · live · Critical IT loadLiveBC Phase 1 critical IT load · 5 MW · available immediately · Critical IT load

HIVE's sourced critical IT-load signal now includes the Boden LOI, but the commercial proof point is conversion from LOI to definitive lease.

Key risk: Boden is a non-binding LOI, not a definitive lease. Most of the 950 MW global power footprint is not sourced as contracted AI critical IT load; GTA and Yguazu remain gross/substation capacity with no named tenant.HIVE BUZZ HPC / GTA / Yguazu / Boden SEC exhibits
AvailableStatusSource-backedSourceOpenAI Stargate updateLast verifiedJun 12, 2026
1 gross capacity phase breakdown
AvailableStargate gross buildout · 5 GW · multi-year · Gross capacity

Use as the scale benchmark for demand, grid stress, and competitive urgency.

Key risk: Large-cap platform exposure; campus cadence can shift without moving the whole stock story.OpenAI Stargate update
WatchlistStatusUnavailableSourceMetaKai source reviewLast verifiedJun 12, 2026
1 reported capacity phase breakdown
UnquantifiedNo source-backed AI/HPC IT load · No reported GW · review · Unavailable

Keep as hardware and high-density compute backlog, not a tradeable AI data-center delivery name.

Key risk: Mining deployments do not validate AI/HPC lease economics.MetaKai source review

Site map

North America site map

Geographic view of site concentration, status, ticker exposure, and selected gross capacity.

Digital assetNeocloudHyperscaleEarly-stageNeeds review
Basemap © OSM
Zoom 4 · dot size uses gross capacity; unavailable or caveated records use minimum size.

Site records

30 records match the current filters.

SiteTickersStatusCategorySelected basis
Helios Data Center Campus
Dickens County / West Texas
GLXYCRWVcontracted developmentConfirmed site
3,500 MWGross capacity
Source-backedGalaxy Q2 2025 updateLast verified Aug 5, 2025Company-disclosed total potential power capacity after adjacent land and 1 GW interconnection-request acquisition; includes currently approved/leased 800 MW gross power and future development capacity, not critical IT load.
Lancaster AI Data Center
Lancaster, Pennsylvania
CRWVannouncedConfirmed site
300 MWGross capacity
Source-backedReuters CoreWeave Lancaster reportLast verified Jul 15, 2025Use as gross/up-to capacity, not critical IT load.
Vineland AI Factory
Vineland, New Jersey
NBISdevelopmentConfirmed site
300 MWGross capacity
Source-backedNebius / Microsoft infrastructure coverageLast verified Sep 9, 2025Reported AI-focused data-center capacity; keep separate from critical IT load.
Independence AI Factory
Independence, Missouri
NBISapprovedDevelopment site
1,200 MWGross capacity
Source-backedNebius Q1 2026 shareholder letterLast verified May 13, 2026Company-source gross/site power for the owned Independence AI factory; do not convert to critical IT load.
Kansas City Colocation
Kansas City, Missouri
NBIScolocationDevelopment site
UnavailableGross capacity
UnavailableNebius / Microsoft infrastructure coverageLast verified Sep 9, 2025Gross site capacity not available because this is a third-party colocation deployment.
Columbiana AI Data Center Campus
Columbiana, Alabama
DGXXannouncedEarly-stage
UnavailableGross capacity
UnavailableDigi Power X 8-KLast verified May 8, 2026Gross power capacity not available from reviewed source.
Abilene Stargate / OCI Campus
Abilene, Texas
ORCLoperational hyperscale siteHyperscale site
1,200 MWGross capacity
Needs verificationReuters Crusoe funding reportLast verified Oct 23, 2025Secondary-reported campus gross-power scale; excluded from default totals until confirmed by OpenAI, Oracle, or another primary site-level source.
Birmingham AI Factory
Birmingham, Alabama
NBISresearch backlog developmentResearch backlog
UnavailableGross capacity
UnavailableNebius Q4/FY 2025 shareholder letterLast verified Feb 12, 2026Alabama/Birmingham site is company-confirmed, but site-specific gross capacity is not disclosed.
Pennsylvania AI Factory Region
Pennsylvania, exact site undisclosed
NBISregional company-confirmed developmentResearch backlog
1,200 MWGross capacity
Source-backedNebius Q1 2026 financial resultsLast verified May 13, 2026Company-source regional gross/site power; exact site remains undisclosed.
Project Horizon
West Texas
CRWVconflicting reportsResearch backlog
2,000 MWGross capacity
DisputedCoreWeave / DCD conflict reviewLast verified Jun 12, 2026Disputed Project Horizon report; exclude from default totals.
Project Dorothy Miner Deployment
Briscoe County, Texas
CANmining deploymentResearch backlog
UnavailableGross capacity
Needs verificationCanaan / Soluna deployment reviewLast verified Jun 12, 2026No AI data-center gross capacity available from reviewed source.
Calgary Gas-to-Computing Pilot
Calgary, Alberta
CANpilotResearch backlog
UnavailableGross capacity
Needs verificationCanaan / Aurora AZ Energy pilot reviewLast verified Jun 12, 2026No AI data-center gross capacity available from reviewed source.
Polaris Forge 1 AI Factory Campus
Ellendale, North Dakota
APLDCRWVcontracted / funded developmentDevelopment site
1,000 MWGross capacity
Source-backedApplied Digital CoreWeave lease releaseLast verified Jun 2, 20251+ GW campus power under load study; do not convert to IT load.
Delta Forge 2 AI Factory Campus
Southern United States, state undisclosed
APLDcontracted developmentDevelopment site
UnavailableGross capacity
UnavailableApplied Digital Delta Forge 2 SEC exhibitLast verified Jun 8, 2026Gross site/grid capacity was not disclosed for Delta Forge 2.
Lake Mariner Data Campus
Barker, New York
WULFoperational and expandingConfirmed site
500 MWGross capacity
Source-backedTeraWulf Q1 2026 10-QLast verified May 8, 2026Near-term gross capacity; potential expansion to 750 MW requires additional approvals.
Abernathy HPC Campus
Abernathy, Texas
WULFcontracted development / pending saleConfirmed site
UnavailableGross capacity
UnavailableTeraWulf Q1 2026 10-QLast verified May 8, 2026Gross power capacity not available from reviewed source.
Cayuga HPC Development Site
Lansing, New York
WULFforward developmentDevelopment site
400 MWGross capacity
Source-backedTeraWulf Q1 2026 10-QLast verified May 8, 2026Potential gross capacity after permitting and site development; not contracted IT load.
Justified Data Campus / Hawesville
Hawesville, Kentucky
WULFcontracted developmentConfirmed site
480 MWGross capacity
Source-backedTeraWulf Q1 2026 10-QLast verified May 8, 2026Gross power availability at the Hawesville Site; keep separate from the 401 MW Anthropic contracted critical IT load.
Muskie Data Campus
Eastern Kentucky / EastPark Industrial Park
WULFdevelopmentDevelopment site
1,000 MWGross capacity
Source-backedTeraWulf Muskie Data Campus SEC exhibitLast verified May 26, 2026More than 1 GW of gross development capacity over time; not contracted critical IT load.
Beacon Point AI Data Center Campus
Nueces County, Texas
HUTcontracted developmentConfirmed site
1,000 MWGross capacity
Source-backedInvestor's Business Daily Hut 8 Beacon Point coverageLast verified May 6, 2026Reported campus electrical utility capacity; not equivalent to critical IT load.
Barber Lake HPC Data Center
Colorado City, Texas
CIFRcontracted developmentConfirmed site
300 MWGross capacity
Source-backedCipher / Fluidstack Barber Lake expansion SEC exhibitLast verified Nov 20, 2025Full Barber Lake site capacity leased to Fluidstack; stored as gross/site capacity, not critical IT load.
Black Pearl Data Center
Winkler County, Texas
CIFRmining / AI-ready developmentDevelopment site
300 MWGross capacity
Source-backedMidland Reporter-Telegram Cipher Black Pearl coverageLast verified Dec 3, 2024Gross power/site capacity only; do not count as contracted IT load.
Rockdale Data Center Site
Rockdale, Texas
RIOTcontracted initial leaseDevelopment site
700 MWGross capacity
Source-backedRiot 2026 business updateLast verified Jan 16, 2026Rockdale site-level interconnection/approved power; not critical IT load and not Riot's broader leasing-opportunity figure.
Sweetwater AI Campus
Sweetwater, Texas
IRENunder constructionConfirmed site
2,000 MWGross capacity
Source-backedIREN Sweetwater siteLast verified Jun 12, 2026Gross power capacity; no IT-load conversion is sourced.
Childress Data Center
Childress, Texas
IRENoperational / AI-readyConfirmed site
750 MWGross capacity
Source-backedIREN Childress siteLast verified Jun 12, 2026Gross power capacity; no critical IT-load conversion is sourced.
Oklahoma Data Center Campus
Oklahoma, USA
IRENin developmentDevelopment site
1,600 MWGross capacity
Source-backedIREN Oklahoma siteLast verified Jun 12, 2026Gross power capacity; no critical IT-load conversion is sourced.
Mackenzie Data Center
Mackenzie, British Columbia
IRENoperationalConfirmed site
80 MWGross capacity
Source-backedIREN Mackenzie siteLast verified Jun 12, 2026Gross power capacity; no critical IT-load conversion is sourced.
Canal Flats Data Center
Canal Flats, British Columbia
IRENoperationalConfirmed site
30 MWGross capacity
Source-backedIREN Canal Flats siteLast verified Jun 12, 2026Gross power capacity; no critical IT-load conversion is sourced.
Prince George Data Center
Prince George, British Columbia
IRENoperational AI Cloud siteConfirmed site
50 MWGross capacity
Source-backedIREN Prince George siteLast verified Jun 12, 2026Gross power capacity; no critical IT-load conversion is sourced.
BUZZ GTA AI Gigafactory
Greater Toronto Area, Ontario
HIVEdevelopmentDevelopment site
320 MWGross capacity
Source-backedHIVE BUZZ GTA SEC exhibitLast verified May 18, 2026Utility capacity allocation; no sourced critical IT-load conversion.